Reconstruction and modernization of the cement plant

Реконструкция и модернизация завода по производству цемента5
  • Investments

    18 500 million rubles

  • Investor

    LLC Holsim (Rus) (Holcim (Rus) (Switzerland)

  • Number of workplaces

    52

  • Project time frame

    06/01/2012 - 08/30/2017

Reconstruction and modernization of the cement plant
Name of the project: Reconstruction and modernization of the plant for the production of cement.

Start date of the project - 2012.

Test run of the project - 2017.

Investment: 18 500,0 million rubles

Investor: Holcim (Rus) (Holcim (Rus) (Switzerland)

Number of of workplaces: 52.

Holcim (Rus) Ltd (the name before the 04.04.2014 "Volskcement") was founded in 1897 by the Petersburg association and the local merchant M.F. Pligin. Currently, it produces portland cement for general construction purposes, sulfate-resistant Portland cement and cement slurry according to the API standard. It has an international quality certificate ISO 9001: 2008. The majority shareholder of Holcim (Rus).

The investment project for the reconstruction and modernization of the plant includes the installation of a new production line for a "semi-dry" production method, with a capacity of 4,500 tons / day. The new project was implemented at the plant in accordance with the Company's development strategy, the concept of social and environmental responsibility and with full compliance with the legislation on environmental protection, labor protection and industrial safety, as well as guarantees of operational reliability.
In 2017, a new technological line was launched in the test mode
Similar stories
card-img

Investments: 557 млн рублей
Инвестор: Investor: ООО «Петровские хлеба»
Number of workplaces: 45
Project time frame: 01/01/2021 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 1 млрд рублей
Инвестор: Investor: ОП АО «БТК Групп»
Number of workplaces: 2500
Project time frame: 01/01/2023 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 1,1 млрд рублей
Инвестор: Investor: ООО «Интэк»
Number of workplaces:
Project time frame: 01/01/2022 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 1,4 млрд рублей
Инвестор: Investor: ООО «Метеор Термотехника Энгельс»
Number of workplaces: 191
Project time frame: 01/01/2013 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 1,9 млрд рублей
Инвестор: Investor: АО «Металлургический завод Балаково»
Number of workplaces: 36
Project time frame: 01/01/2021 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 2 млрд рублей
Инвестор: Investor: ООО «Грачевка»
Number of workplaces: 100
Project time frame: 01/01/2022 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 4,8 млрд руб
Инвестор: Investor: АО «Апатит»
Number of workplaces: 28
Project time frame: 01/01/2020 - 01/01/2024
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 2,6 млрд рублей
Инвестор: Investor: АО «ЕПК Саратов»
Number of workplaces: 200
Project time frame: 01/01/2019 - 01/01/2025
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 2 млрд рублей
Инвестор: Investor: АО «Металлургический завод Балаково»
Number of workplaces: 68
Project time frame: 01/01/2021 - 01/01/2025
08/18/2025 11:00:00 pm More detailed
card-img

Investments: 2 млрд рублей
Инвестор: Investor: ООО «А-сервис»
Number of workplaces: 692
Project time frame: 01/01/2023 - 01/01/2025
08/18/2025 11:00:00 pm More detailed