Investment map

Distribution center construction
Строительство распределительного центра
  • Investments

    600 million rubles

  • Investor

    X5 Retail Group (Russian retailer, owner of retail chains Pyaterochka, Perekrestok, Karusel, Kopeyka)

  • Number of workplaces

    300

  • Project time frame

    08/01/2017 - 11/03/2018

Distribution center construction
Project name: Construction of a distribution center
Project start: 2017
Completion of the project: November 2018
Investor: X5 Retail Group (Russian retailer, owner of retail chains Pyaterochka, Perekrestok, Karusel, Kopeyka)
Amount of investments: 600 million rubles
Number of jobs created: 300

Construction in the Saratov municipal district of a distribution center with an area of ​​16 thousand sq. m. with a capacity of more than 100 trucks per day.
Similar stories
card-img

Investments: 400 million rubles
Инвестор: Investor: Peasant farm "Agros"
Number of workplaces: 12
Project time frame: 01/01/2019 - 01/01/2023
02/07/2024 01:00:00 am More detailed
card-img

Investments: 389 million rubles
Инвестор: Investor: LLC "Rusagro-Balakovo"
Number of workplaces: -
Project time frame: 01/01/2020 - 01/01/2023
02/07/2024 More detailed
card-img

Investments: 412 million rubles
Инвестор: Investor: EPO Signal LLC
Number of workplaces: 38
Project time frame: 01/01/2018 - 01/01/2023
02/07/2024 More detailed
card-img

Investments: 213 million rubles
Инвестор: Investor: Engels Spark Plugs LLC
Number of workplaces:
Project time frame: 01/01/2022 - 01/01/2023
02/07/2024 More detailed
card-img

Investments: 371 million rubles
Инвестор: Investor: JSC Breeding plant "Trudovoy"
Number of workplaces:
Project time frame: 01/01/2022 - 01/01/2023
02/07/2024 More detailed
card-img

Investments: 50 million rubles
Инвестор: Investor: JSC BTK Group
Number of workplaces: 210
Project time frame: 02/07/2022 - 02/07/2023
02/07/2024 More detailed
card-img

Investments: 500 million rubles
Инвестор: Investor: OOO "Trading House Grain of the Volga Region"
Number of workplaces: 60
Project time frame: 03/01/2020 - 12/01/2022
02/27/2023 01:00:00 am More detailed
card-img

Investments: 2.7 billion rubles
Инвестор: Investor: Green Energy Rus LLC
Number of workplaces:
Project time frame: 02/18/2021 - 06/01/2022
02/27/2023 01:00:00 am More detailed
card-img

Investments: 469 million rubles
Инвестор: Investor: JSC Balakovo-Centrolit
Number of workplaces: 127
Project time frame: 01/01/2017 - 02/01/2022
02/27/2023 01:00:00 am More detailed
card-img

Investments: 594 million rubles
Инвестор: Investor: LLC Agrofirma Rubezh
Number of workplaces: 30
Project time frame: 01/01/2021 - 12/01/2021
02/27/2023 01:00:00 am More detailed
Ask a question
Fill out the form and we will contact you as soon as possible
Ask a question
Fill out the form and we will contact you as soon as possible
Enter your full name
Enter your Email Address
Describe the essence of the question or suggestion

By filling out the feedback form, you agree to the privacy Policy.