Construction of a new steel molding plant for railway coach manufacturing
-
Investments
4200,0 million rubles
-
Investor
JSC “Balakovo-Centrolit”
-
Number of workplaces
164
-
Project time frame
03/11/2012 - 05/29/2014
Project name: Construction of a new steel molding plant for railway coach manufacturing.
Start date of the project – 2012.
Project completion date – 2014.
Investment: 4200,0 million rubles.
Investor: JSC “Balakovo-Centrolit”.
Number of workplaces: 164.
The project was implemented in the territory of the Balakovsky Municipal District.
18000 tons of founding per year.
Founding of metallic parts for the railway rolling stock and their delivery at JSC "Zavod Metallokonstruktsy" (Engels), as well as partly at JSC “Vagonostroitelny Zavod” (Balakovo).
Previously, large companies in Russia were forced to buy details such as "beam bolster" and "side frame" abroad. This plant became an effective example of the import substitution program.