Modernization of hydraulic turbines stage No. 1-21, 24
Type of works:
Modernization
Custumer:
PJSC "RusHydro" Branch "Saratov HPP"
Total volume of investments:
63 400 000,00 тыс. руб.
incl.extrabudgetary:
63 400 000,00 тыс. руб.
Location of the object:
Balakovo municipal district of the region
Term of realization:
2011-2028
Degree of readiness:
Construction and installation work is being carried out on gas turbines: station No. 1, station No. 5, station No. 9
Reconstruction of 40 boiler houses with installation of cabinet-type boilers, transfer of loads from 8 boiler houses to the network of Saratov CHPP-5, construction of a hot water boiler, KVGM-140-150 at Saratov CHPP-2
Type of works:
Reconstruction
Custumer:
Branch "Saratov" PJSC "T Plus"
Total volume of investments:
572 000,00 тыс. руб.
incl.extrabudgetary:
572 000,00 тыс. руб.
Location of the object:
Saratov
Term of realization:
2019-2020
Investment program of TK TURA LLC in the field of heat supply
Type of works:
2020-2023
Total volume of investments:
146 600,00 тыс. руб.
incl.extrabudgetary:
146 600,00 тыс. руб.
Location of the object:
Engelssky municipal district
Technical re-equipment of sections of the main heating network
Type of works:
Technical re-equipment
Custumer:
Branch "Saratov" PJSC "T Plus"
Total volume of investments:
4 300 000,00 тыс. руб.
Location of the object:
Municipal entity "City of Saratov", Balakovo municipal district, Engels municipal district
Term of realization:
2019-2024
Degree of readiness:
Work in progress